Project Name
NYPA Green Hydrogen Demonstration Project
GPS Coordinates
POINT (-73.2462 40.7812)
Project Summary

The project will co-fire hydrogen with natural gas at NYPA's Brentwood Power Station on Long Island. The simple-cycle plant consists of a GE LM-6000 gas turbine commissioned in the summer of 2001. Different concentrations of hydrogen (0-35% by volume) will be blended and co-fired with natural gas at regular intervals to assess the impact on greenhouse gas emissions, NOx emissions and overall system performance. The hydrogen co-firing tests will begin in spring 2022 and are expected to last six to eight weeks.

Custom Beginning Date
Spring 2022
Custom Ending Date
Summer 2022
Project Status
In Progress
Utilities
Vendors